Bid Abstract

SAP 043-603-031 - Grading & Concrete Paving CSAH 3 from CSAH 1 to CSAH 9 (3 other tied projects also, see Ad for Bid)S.M. Hentges & Son, Inc. Mathiowetz Construction Shafer Contracting Co. Inc. PCI Roads Knife River Midwest, LLC Duininck, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2011.601CONSTRUCTION SURVEYINGLS1$39,239.40$39,239.40$40,000.00$40,000.00$42,000.00$42,000.00$38,470.00$38,470.00$78,951.48$78,951.48$49,650.00$49,650.00
2021.501MOBILIZATIONLS1$16,243.47$16,243.47$223,890.50$223,890.50$115,000.00$115,000.00$160,400.00$160,400.00$113,938.26$113,938.26$180,000.00$180,000.00
2101.511CLEARING AND GRUBBINGLS1$5,780.00$5,780.00$5,667.00$5,667.00$10,000.00$10,000.00$5,667.00$5,667.00$5,840.97$5,840.97$16,000.00$16,000.00
2104.501REMOVE PIPE CULVERTSL F1,082$10.49$11,350.18$6.00$6,492.00$10.00$10,820.00$5.90$6,383.80$6.08$6,578.56$8.25$8,926.50
2104.501REMOVE FENCEL F220$2.29$503.80$1.00$220.00$5.00$1,100.00$5.00$1,100.00$5.15$1,133.00$4.75$1,045.00
2104.509REMOVE LIGHT BASE FOUNDATIONEACH1$570.64$570.64$250.00$250.00$1,000.00$1,000.00$500.00$500.00$515.35$515.35$2,000.00$2,000.00
2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)L F230$2.30$529.00$2.25$517.50$10.00$2,300.00$2.25$517.50$2.32$533.60$2.25$517.50
2104.523SALVAGE LIGHT POLEEACH1$352.32$352.32$1,600.00$1,600.00$1,000.00$1,000.00$1,600.00$1,600.00$824.56$824.56$1,600.00$1,600.00
2104.523SALVAGE PIPE APRONEACH2$352.33$704.66$100.00$200.00$500.00$1,000.00$160.00$320.00$164.91$329.82$610.00$1,220.00
2105.604GEOTEXTILE FABRIC TYPE IS Y335$3.42$1,145.70$6.00$2,010.00$25.00$8,375.00$4.00$1,340.00$4.12$1,380.20$5.00$1,675.00
2105.607HAUL AND STOCKPILE EXCESS MATERIALC Y7,485$7.48$55,987.80$6.99$52,320.15$10.00$74,850.00$24.00$179,640.00$15.46$115,718.10$24.00$179,640.00
2106.501EXCAVATION - COMMON (P)C Y96,603$1.88$181,613.64$2.58$249,235.74$4.00$386,412.00$2.60$251,167.80$2.68$258,896.04$1.85$178,715.55
2106.523COMMON EMBANKMENT (CV) (P)C Y107,198$3.82$409,496.36$2.58$276,570.84$3.50$375,193.00$5.50$589,589.00$5.67$607,812.66$6.26$671,059.48
2106.619SURFACE PREPARATIONRDST130$288.77$37,540.10$50.00$6,500.00$100.00$13,000.00$415.00$53,950.00$427.74$55,606.20$360.00$46,800.00
2111.501TEST ROLLING (P)RDST130$326.00$42,380.00$30.00$3,900.00$100.00$13,000.00$70.00$9,100.00$72.15$9,379.50$115.00$14,950.00
2123.501COMMON LABORERSHOUR50$90.73$4,536.50$75.00$3,750.00$100.00$5,000.00$85.00$4,250.00$87.61$4,380.50$80.00$4,000.00
2123.509DOZERHOUR20$179.70$3,594.00$189.00$3,780.00$150.00$3,000.00$180.00$3,600.00$185.53$3,710.60$165.00$3,300.00
2123.610TRACTOR MOUNTED BACKHOE-LOADERHOUR50$225.81$11,290.50$140.00$7,000.00$150.00$7,500.00$180.00$9,000.00$185.53$9,276.50$140.00$7,000.00
2211.501AGGREGATE BASE CLASS 5TON14,178$14.39$204,021.42$14.75$209,125.50$15.00$212,670.00$18.80$266,546.40$18.35$260,166.30$22.00$311,916.00
2215.501FULL DEPTH RECLAMATION (P)S Y38,778$6.14$238,096.92$5.57$215,993.46$1.18$45,758.04$2.60$100,822.80$3.29$127,579.62$5.50$213,279.00
2215.604INCORPORATION OF LIQUID STABILIZING MATERIAL (P)SY46,676$0.48$22,404.48$0.62$28,939.12$0.38$17,736.88$1.29$60,212.04$0.72$33,606.72$1.00$46,676.00
2221.501SHOULDER BASE AGGREGATE CLASS 5 MODTON2,785$9.41$26,206.85$18.86$52,525.10$15.65$43,585.25$27.25$75,891.25$20.61$57,398.85$20.00$55,700.00
2232.501"MILL BITUMINOUS SURFACE (3.0"")" (P)S Y34,680$0.91$31,558.80$1.80$62,424.00$0.42$14,565.60$1.52$52,713.60$1.65$57,222.00$1.50$52,020.00
2301.504"PLACE CONCRETE PAVEMENT 8""" (P)S Y41,023$6.95$285,109.85$5.55$227,677.65$8.00$328,184.00$5.55$227,677.65$5.90$242,035.70$5.55$227,677.65
2301.508SUPPLEMENTAL PAVEMENT REINFORCEMENTLB2,200$4.02$8,844.00$1.70$3,740.00$2.00$4,400.00$1.70$3,740.00$3.34$7,348.00$1.70$3,740.00
2301.511STRUCTURAL CONCRETE (P)C Y9,072$101.30$918,993.60$103.50$938,952.00$98.00$889,056.00$103.50$938,952.00$109.30$991,569.60$103.50$938,952.00
2301.601Concrete W/C Ratio Incentive/DisincentiveLump Sum1$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00$24,000.00
2301.602"1.25"" DOWEL BAR"EACH10,694$5.65$60,421.10$7.45$79,670.30$5.42$57,961.48$7.45$79,670.30$7.51$80,311.94$7.45$79,670.30
2357.502BITUMINOUS MATERIAL FOR TACK COATGAL240$5.10$1,224.00$5.00$1,200.00$5.00$1,200.00$4.00$960.00$2.06$494.40$2.50$600.00
2360.501TYPE SP 12.5 WEARING COURSE MIXTURE (2,C)TON398$85.68$34,100.64$84.00$33,432.00$84.00$33,432.00$109.00$43,382.00$84.00$33,432.00$92.00$36,616.00
2360.502TYPE SP 12.5 NON WEARING COURSE MIXTURE (2,C)TON796$80.58$64,141.68$79.00$62,884.00$79.00$62,884.00$95.00$75,620.00$82.46$65,638.16$93.50$74,426.00
2399.601Concrete Ride Incentive/DisincentiveLS1$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00$35,000.00
2451.511COARSE FILTER AGGREGATE (LV)C Y85$76.88$6,534.80$80.00$6,800.00$100.00$8,500.00$60.00$5,100.00$61.84$5,256.40$100.00$8,500.00
2501.511"18"" CS PIPE CULVERT"L F1,384$32.65$45,187.60$24.00$33,216.00$35.00$48,440.00$44.50$61,588.00$45.87$63,484.08$40.00$55,360.00
2501.511"24"" RC PIPE CULVERT"L F396$55.31$21,902.76$45.00$17,820.00$50.00$19,800.00$60.00$23,760.00$61.84$24,488.64$75.00$29,700.00
2501.511"36"" RC PIPE CULVERT"L F128$98.91$12,660.48$84.00$10,752.00$125.00$16,000.00$107.00$13,696.00$110.28$14,115.84$125.00$16,000.00
2501.569"36"" RC SAFETY APRON"EACH2$1,940.08$3,880.16$1,718.00$3,436.00$3,500.00$7,000.00$2,320.00$4,640.00$2,391.22$4,782.44$2,000.00$4,000.00
2501.569"18"" GS SAFETY APRON"EACH42$341.20$14,330.40$202.00$8,484.00$250.00$10,500.00$550.00$23,100.00$566.88$23,808.96$275.00$11,550.00
2501.569"24"" RC SAFETY APRON"EACH10$856.29$8,562.90$587.00$5,870.00$950.00$9,500.00$900.00$9,000.00$927.63$9,276.30$680.00$6,800.00
2502.541"6"" PERF PE PIPE DRAIN"L F285$8.22$2,342.70$10.00$2,850.00$20.00$5,700.00$18.80$5,358.00$19.38$5,523.30$15.00$4,275.00
2502.541"8"" PERF PE PIPE DRAIN"L F1,365$14.04$19,164.60$8.00$10,920.00$25.00$34,125.00$18.80$25,662.00$19.38$26,453.70$16.00$21,840.00
2502.602"12"" PE INSPECTION TEES"EACH6$784.93$4,709.58$725.00$4,350.00$1,500.00$9,000.00$1,000.00$6,000.00$1,030.70$6,184.20$760.00$4,560.00
2502.6026" PE PIPE DRAIN INLETEACH1$473.51$473.51$375.00$375.00$1,000.00$1,000.00$365.00$365.00$376.21$376.21$550.00$550.00
2502.602"6"" PE INSPECTION TEES"EACH4$264.54$1,058.16$380.00$1,520.00$250.00$1,000.00$365.00$1,460.00$376.21$1,504.84$200.00$800.00
2502.602"8"" PE INSPECTION TEES"EACH4$331.17$1,324.68$355.00$1,420.00$250.00$1,000.00$420.00$1,680.00$432.89$1,731.56$300.00$1,200.00
2502.60210"" PE INSPECTION TEES"EACH2$503.72$1,007.44$534.00$1,068.00$500.00$1,000.00$560.00$1,120.00$577.20$1,154.40$550.00$1,100.00
2503.5116" SDR 35 PVC Pipe SewerLin FT270$10.11$2,729.70$24.00$6,480.00$20.00$5,400.00$33.00$8,910.00$34.01$9,182.70$23.00$6,210.00
2503.5118" SDR 35 PVC Pipe SewerLin FT230$11.93$2,743.90$25.00$5,750.00$25.00$5,750.00$39.50$9,085.00$40.71$9,363.30$25.00$5,750.00
2503.51110" SDR 35 PVC Pipe SewerLin Ft150$14.26$2,139.00$29.00$4,350.00$28.00$4,200.00$41.50$6,225.00$42.77$6,415.50$32.00$4,800.00
2503.51112" SDR 35 PVC Pipe SewerLin Ft120$14.87$1,784.40$31.00$3,720.00$30.00$3,600.00$46.50$5,580.00$47.93$5,751.60$34.00$4,080.00
2503.51116" SDR 35 PVC Pipe SewerLin Ft150$30.79$4,618.50$37.00$5,550.00$35.00$5,250.00$49.00$7,350.00$50.50$7,575.00$45.00$6,750.00
2503.51118" SDR 35 PVC Pipe SewerLin Ft140$39.45$5,523.00$46.00$6,440.00$50.00$7,000.00$59.00$8,260.00$60.81$8,513.40$60.00$8,400.00
2511.502RANDOM RIPRAP CLASS IIITON20$107.62$2,152.40$70.00$1,400.00$100.00$2,000.00$80.00$1,600.00$82.46$1,649.20$85.00$1,700.00
2515.503ARTICULATED INTERLOCKING BLOCK OPEN CELL,TYPE AS Y54$127.22$6,869.88$170.00$9,180.00$150.00$8,100.00$102.00$5,508.00$105.13$5,677.02$105.00$5,670.00
2540.602RELOCATE MAIL BOX SUPPORTEACH11$51.00$561.00$50.00$550.00$50.00$550.00$50.00$550.00$51.53$566.83$50.00$550.00
2540.602MAIL BOX SUPPORTEACH11$102.00$1,122.00$110.00$1,210.00$110.00$1,210.00$110.00$1,210.00$103.07$1,133.77$110.00$1,210.00
2545.602INSTALL LIGHTING UNITEACH1$4,590.00$4,590.00$2,800.00$2,800.00$2,500.00$2,500.00$2,800.00$2,800.00$10,822.34$10,822.34$2,800.00$2,800.00
2554.501TRAFFIC BARRIER DESIGN SPECIALL F100$88.23$8,823.00$86.50$8,650.00$86.50$8,650.00$86.50$8,650.00$89.16$8,916.00$86.50$8,650.00
2554.501TRAFFIC BARRIER DESIGN B8338L F350$19.38$6,783.00$19.00$6,650.00$19.00$6,650.00$19.00$6,650.00$19.58$6,853.00$19.00$6,650.00
2554.523END TREATMENT-TANGENT TERMINALEACH4$2,652.00$10,608.00$2,600.00$10,400.00$2,600.00$10,400.00$2,600.00$10,400.00$2,679.82$10,719.28$2,600.00$10,400.00
2563.601TRAFFIC CONTROLLS1$5,304.00$5,304.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$8,245.59$8,245.59$6,000.00$6,000.00
2573.502SILT FENCE, TYPE MSL F9,000$1.73$15,570.00$1.70$15,300.00$1.70$15,300.00$2.10$18,900.00$2.16$19,440.00$1.70$15,300.00
2573.533SEDIMENT CONTROL LOG TYPE WOOD FIBERL F1,685$2.52$4,246.20$2.47$4,161.95$2.47$4,161.95$2.60$4,381.00$2.68$4,515.80$2.47$4,161.95
2573.550EROSION CONTROL SUPERVISORLS1$12,108.60$12,108.60$1,000.00$1,000.00$2,500.00$2,500.00$5,000.00$5,000.00$5,153.49$5,153.49$1,500.00$1,500.00
2574.508FERTILIZER TYPE 1LB6,000$0.56$3,360.00$0.55$3,300.00$0.55$3,300.00$0.50$3,000.00$0.52$3,120.00$0.55$3,300.00
2574.550COMPOST GRADE 2C Y125$87.10$10,887.50$53.00$6,625.00$100.00$12,500.00$50.00$6,250.00$51.53$6,441.25$85.00$10,625.00
2575.501SEEDINGACRE37$76.50$2,830.50$75.00$2,775.00$75.00$2,775.00$150.00$5,550.00$154.60$5,720.20$75.00$2,775.00
2575.502SEED MIXTURE 25-142LB1,350$3.57$4,819.50$3.50$4,725.00$3.50$4,725.00$3.10$4,185.00$3.20$4,320.00$3.50$4,725.00
2575.502SEED MIXTURE 25-151LB840$2.89$2,427.60$2.83$2,377.20$2.83$2,377.20$3.15$2,646.00$3.25$2,730.00$2.83$2,377.20
2575.511MULCH MATERIAL TYPE 3TON74$255.00$18,870.00$250.00$18,500.00$250.00$18,500.00$175.00$12,950.00$180.37$13,347.38$250.00$18,500.00
2575.519DISK ANCHORINGACRE37$76.50$2,830.50$75.00$2,775.00$75.00$2,775.00$50.00$1,850.00$51.53$1,906.61$75.00$2,775.00
2575.523EROSION CONTROL BLANKETS CATEGORY 3S Y5,990$1.28$7,667.20$1.25$7,487.50$1.25$7,487.50$0.99$5,930.10$1.02$6,109.80$1.25$7,487.50
2575.571RAPID STABILIZATION METHOD 3MGAL14$341.70$4,783.80$335.00$4,690.00$335.00$4,690.00$200.00$2,800.00$206.14$2,885.96$335.00$4,690.00
2582.502"6"" SOLID LINE PAINT"L F26,856$0.20$5,371.20$0.20$5,371.20$0.30$8,056.80$0.188$5,048.93$0.19$5,102.64$0.19$5,102.64
2582.502"4"" SOLID LINE PAINT"L F1,000$0.16$160.00$0.16$160.00$0.26$260.00$0.157$157.00$0.16$160.00$0.16$160.00
2582.502"4"" BROKEN LINE PAINT"L F2,626$0.16$420.16$0.16$420.16$0.26$682.76$0.157$412.28$0.16$420.16$0.16$420.16
2582.603FORMED 4" GROOVE FOR PAINT STRIPELIN FT25,912$0.01$259.12$0.01$259.12$0.16$4,145.92$0.01$259.12$0.01$259.12$0.01$259.12
2582.603FORMED 6" GROOVE FOR PAINT STRIPELIN FT25,912$0.01$259.12$0.01$259.12$0.20$5,182.40$0.01$259.12$0.01$259.12$0.01$259.12
 Totals for project SAP 043-603-031 $3,083,343.96 $3,127,664.11 $3,190,227.78 $3,652,668.69 $3,662,026.12 $3,798,644.67
 
Contract Total:$3,083,343.96$3,127,664.11$3,190,227.78$3,652,668.69$3,662,026.12$3,798,644.67